A 77-acre site designed around the existing wetlands to promote future sustainability.  The finished school will include full athletic facilities including the football stadiums.  The open-air campus design will hold three main buildings. 

 

The three primary buildings include the main building which will house classrooms and administrative offices, the second building will consist of the gymnasium, kitchen, and cafeteria, and the third is an auditorium for band and music use.  This school will provide several unique academies to our areas youth, some of which are the Academy of Health Professionals, Air Force Junior ROTC, Sustainable Agriculture and Entrepreneurship, FGCU Collegiate Academy, Computer Science Academy, Aerospace Academy, and the Education Academy & Environmental Academy. 

Project Size: 220,000 sqft. | Start Date: 01.2017 | Completion Date: 02.2018

 BONITA SPRINGS HIGH SCHOOL

Anchor 1
Test_edited.jpg
Mariner.bmp
7acdf294-55ca-4005-ae58-c0ba8849f824-646
016.bmp

Due to Hurricane Irma, the roofing labor forces required to complete this project were in high demand. 

 

It was extremely important to us that we stuck to the schedule we delivered to the owner.  Through precise communication and coordination of subcontractors, we were able to deliver this project on budget and within the time constraints set forth by the district. 

Project Size: 290,000 sqft. | Start Date: 03.2018 | Completion Date: 02.2019

MARINER HIGH SCHOOL

Anchor 4

Due to Hurricane Irma, the roofing labor forces required to complete this project were in high demand. 

 

It was extremely important to us that we stuck to the schedule we delivered to the owner.  Through precise communication and coordination of subcontractors, we were able to deliver this project on budget and within the time constraints set forth by the district. 

Project Size: 275,000 sqft. | Start Date: 12.2017 | Completion Date: 10.2018
08
Anchor 3

ESTERO HIGH SCHOOL

Anchor 2

Re-Roof in accordance with standards set forth by The School District of Lee County due to Hurricane Irma.

 

It was extremely important to us that we stuck to the schedule we delivered to the owner.  Through precise communication and coordination of subcontractors, we were able to deliver this challenging project on budget and met the deadline while students and staff present during the construction process.

Project Size: 180,000 sqft. | Start Date: 12.2017 | Completion Date: 09.2018